Newfoundland & Labrador
Explore what’s being built, where it is, and who’s hiring.
35 projects · 11 under construction
34 projects
34 projects
St. John's
$693M · 2025–2029
The replacement for Her Majesty's Penitentiary — the province's largest building project, running to 2029.
Holyrood
$891M · 2026–2030
A roughly 150 MW combustion turbine at Holyrood — an $891M, four-year program starting on site in 2026.
Come By Chance
$1.8B · Until Dec 2030
45 turbines and a hydrogen plant near Sunnyside — the one NL wind-hydrogen project still clearly moving.
Labrador
A 2,700 MW dam on the Churchill River — agreed in principle in August 2026, not sanctioned, in service 2036-37.
Channel-Port aux Basques
$270M · From Jun 2026
$270M of federal work on the ferry terminals at Port aux Basques and Argentia, with procurement beginning.
Central
$436M · 2026–2028
Doubling the mill at Valentine Lake from 2.5 to 5.0 Mtpa — approved in August 2026, construction starting now.
Happy Valley-Goose Bay
$187M · 2026–2030
A $187M conversion of the base heating plant from diesel to electric, running May 2026 to December 2030.
Central
$1.1B · From Jan 2028
A proposed eighth generating unit at Bay d'Espoir — the cost and the schedule are both being publicly challenged.
St. John's
A deepwater oil development in the Flemish Pass — still not sanctioned, with a final decision targeted for early 2027.
Western
A 150-bed long-term care home at Stephenville Crossing — the site was expropriated in 2025, construction is still to be scheduled.
Come By Chance
A proposed sustainable-aviation-fuel expansion at Come By Chance. The refinery runs; Phase II is a plan only.
Churchill Falls
Proposed upgrades at Churchill Falls plus 2,000 MW of Labrador wind — the expansion was pulled from the 2026 deal.
Clarenville
A 54-bed long-term care home for Clarenville — planning money only so far, no tender yet.
Conception Bay South
$16M
A 100,000 sq ft recreation centre for CBS — the design was reworked in 2026 and the opening date is open again.
Argentia
$100M · 2026–2027
A 448-metre dock with three berths and a roll-on/roll-off ramp at Argentia — funded, but reported to be at risk.
Corner Brook
$21M · 2025–2028
Converting the old Western Memorial hospital into a community health centre with 45 more long-term care beds.
Deer Lake
$60M · From Apr 2027
About 2,000 m² more terminal at Deer Lake, tender-ready in early 2027.
Central
$25.8M · From Apr 2025
A $25.8M extension and redevelopment of Dorset Collegiate at Pilley's Island, under way now.
Gander
$5.7M · 2026–2028
$5.65M of water and sewer replacement on two Gander streets, funded and running 2026 to 2028.
Wabush
An iron ore mine southwest of Wabush — feasibility study due end of 2026, then a 48-month build if it is sanctioned.
St. John's
$41.9M · Until Aug 2027
An 860-student school in Kenmount Terrace, about 35% built as of spring 2026.
Labrador City
$1B
A 735 kV line from Churchill Falls to Labrador City with a new terminal station — engineering through 2026.
Central
$7.7M · 2026–2028
A $7.68M replacement water treatment plant for Lumsden, funded for 2026 to 2028.
Corner Brook
$9.8M · 2026–2027
A 20-unit affordable apartment building on Crestview Avenue — contract awarded, starting summer 2026.
Happy Valley-Goose Bay
$22M · 2026–2028
$22M to redevelop Paddon Home and add eight transitional beds at the Labrador Health Centre.
St. John's
Between 1,000 and 1,300 new homes on the old Pleasantville lands, with a builder partner still to be chosen.
St. John's
$139M · 2028–2031
Adding secondary treatment at Riverhead — a process build with about two years of design ahead of it.
Rocky Harbour
$7M · 2026–2028
A $6.96M new water supply for Rocky Harbour in Gros Morne, funded for 2026 to 2028.
Eastern (Burin & Bonavista)
May 2026
Rebuilding the Bonavista Highway between Lethbridge and Southern Bay in the 2026-27 season.
St. Anthony
$5.4M · 2026–2028
A $5.44M waterline replacement on East Street in St. Anthony, funded for 2026 to 2028.
St. John's
$30M · 2024–2026
The last 3.3 km of Team Gushue Highway, on track to open in the fall of 2026.
Bishop's Falls
From May 2026
Fifteen kilometres of TCH twinning between Bishop's Falls and Grand Falls-Windsor, from 2026 onward.
Whitbourne
From May 2026
About 40 km of TCH twinning west of Whitbourne, now being let as traditional contracts after the P3 was cancelled.
Argentia
$2B · Until Dec 2026
The concrete gravity structure and topsides at Argentia — about 85% done, with first oil expected in 2026.
Where this comes from.
Every project links to the announcement it came from — a government release, the proponent, or local news. Values and dates are whatever was made public; when nothing was published we leave it blank instead of guessing.
Last updated October 30, 2026.
Know a project we’re missing?